AusLegal.ai

Guides · Queensland

QLD fencing notice: Form 2, then one month to agree

In Queensland, give your neighbour Form 2 (notice to contribute for fencing work) with a quote. No agreement in one month? Apply to QCAT within two months.

Taken from public government information. Internal review done · last reviewed 19 November 2026. General information, not legal advice. How we review.

Part of: Dividing fences in Australia: fencing notice by state

In Queensland, the fencing notice is Form 2, "Notice to contribute for fencing work" (Form 1 is for urgent work). You can't apply to QCAT or the Magistrates Court about a dividing fence dispute unless you have given this notice. If you haven't agreed within one month, you have until two months after the notice is given to apply to QCAT.

General information only, not legal advice.

Key facts

WhatAnswerSource
Default cost splitEach neighbour is liable for half the cost of fencing work. If one neighbour wants more than a "sufficient dividing fence", they pay the extraQueensland Government, fence owner page
Official forms"Form 2 - Notice to contribute for fencing work" and "Form 1 - Notice to contribute for urgent fencing work", published by the Queensland GovernmentQueensland Government, notices to neighbours
What the notice includesThe common boundary to be fenced, the kind of fence, a proposal with estimated cost, the neighbour's proposed contribution and method of construction. At least one written quote must be supplied (two is the courtesy). Form 2 also asks for a signed "Agreement to contribute" to be returned within one monthQCAT; Form 2
How to serveThe pages read say "give" or "deliver (serve)" the notice but do not say how. Not confirmed here. Keep a copy and note the date it was givenQCAT; Form 2
Waiting periodOne month after the notice is givenQCAT; Form 2
Deadline to applyWithin two months after the notice is givenQCAT; Form 2
WhereQCAT, or the Magistrates Court. QCAT hears dividing fence disputes valued up to and including $25,000 (unlimited if the fence is part of a pool barrier)QCAT
If they refuseYou must not go ahead and build or repair the fenceQCAT
Urgent repairsIf a dividing fence is damaged or destroyed and urgent work is needed, do the work and give a notice to contribute for urgent fencing work as soon as possible afterwards. You must give a copy before applying to QCAT. Same one-month and two-month periodsQCAT; Form 1
TenantsFence issues are mostly for owners to solve. A tenant without a long-term lease should refer queries to the owner or agentQueensland Government, fence owner page

Steps

  1. Talk face to face first and try to agree. Write down what you agree.
  2. Get at least one written quote. The page says two is a courtesy.
  3. Complete Form 2 and attach a quote. Keep a copy and note the date you gave it.
  4. Wait one month for the signed agreement or a refusal.
  5. If you haven't agreed, a Dispute Resolution Centre can give free mediation help. QCAT's page says any application must still be made within two months of the notice.
  6. Apply to QCAT within two months of the notice using Form 53 (Application for minor civil dispute - dividing fences). Check the current fee with QCAT before you lodge.

Common mistakes

Where sources differ

The Queensland Government fence owner page calls the Act the "Neighbourhood Disputes Resolution Act 2011" in two places and the "Neighbourhood Disputes (Dividing Fences and Trees) Act 2011" elsewhere. QCAT and Form 2 use the second name, which this guide uses.

Get free help

Official sources

Related guides and answers